Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

give differnt wight to activity's

No replies
Doron El
User offline. Last seen 11 years 22 weeks ago. Offline
Joined: 9 Dec 2010
Posts: 3
Groups: None

hello all
i need your help.
i need to give weight to each activity in the project.
for exmaple here are some activity's i'm dealing with:
1-purchase.=10%
2-Infrastructure installation=30%
3-instrument installation=40%
4-delivery=20%

for each activity i need to  take the percent of the activity that finished  and calculate a diffrent weight in  percentages