Hi guys,
I'm new to planning and am still finding my way round the P6 software. If someone could help me I'd be really grateful.
I have a large number of activities and am trying to group a small set of activities by the actual day e.g. On 1st December, these activities will be in progress. On 2nd December these activities will be in progress.
I have tried grouping by start date as most activies are only 1 day duration, but am looking to be complete. Is this possible in P6 v7.0? I realise this will involve duplication of activities.
Thanks
Andy