Dear all
i have a query regarding the % complete type for the activities
i have to use the units % complete for 60% of activities (these activites are totally dependent on the resourceas available)
around 20% activities are based on the duration type(here resources does not matter only duration counts)
around 10% activities are dased on physical % complete(the actitites should be assessed by the % scope finished)
SO IF I USE these three % complete type in a single project what should be my settings while updating the schedule
i wanted to known if the percentages will show correctly when it is rolled up to the wbs level.
please guide me
thanks in advance