START Date:
March, 2008
END Date:
October, 2008 Lead Planner on Stations East Projects for Metronet Alliance
- Reported programme status for stations in the East of London to the Senior Management team outlining key issues, maintaining a strict focus on delivery.
- Managed a team of sixteen planners, meeting periodically to get an understanding of the key issues and mitigation measures taking place on the projects.
- Working with QS fully cost loaded programmes to activity level to ensure accurate EV data.
- Produced recovery programmes to minimise slippage of station projects.
- Reported Project Progress and Earned Value data to LUL and Metronet Rail.
- Created construction programme for Mile End Station Modernisation project integrating a large number of subcontractor plans.
- Shadowed less experienced planners to ensure that contractor programmes showing slippage were recorded against the baseline and reason agreed with sub contractor to minimise EOT claims.