Hello Planners,
Am having difficulty in schedule I've created where I've assigned particular resources that use a 5 day calendar instead of the 6 day applied to the rest of the project.
All good as I know no concrete pours will occour on a Saturday however the critical path now sees a gap between the tasks and doesn't show for these tasks now.
Can work around by entering 1 day gap to show nearly critical but when you filter by critical it only shows those with 0 gap - true critical path.
Anyone had this issue and found a fix?
Kind regards,
Craig Adams