Projects: Electrified Double Track Project Between Rawang - Ipoh
01/2005 – 08/2006
Responsibilities:
•Assist Project Management in detail clarification of ongoing issues including confidential issues (“Sub-Projects within the Project”)
•Assist in managing the process of developing integrated strategic and operational plans for the project
•Assistance in preparation of presentations for strategic issues and phase transition proposals at decision committees such as Steering Committees
•Assistance in optimizing and track progress of project plans (time, resources) and to ensure adherence to plan and strategy
•Monitor, Control and Update the Risk Management Lists
•Assist Project Director to set the yearly goal/ Project Target by forecasting on the project planning
•Support Management of Technical Job Packages
•Liaison with Consortium Partners, Siemens Switzerland and Siemens Malaysia on all project related issues
•Implementation, co-ordination and update of PM@Siemens principles, supervision of adherence to execution plan of milestones after implementation
•Supervision of Controlling, Reporting and Progress Monitoring on Subcontract Manager
•Assist Supply and Sub-Contract Supervision
•Support Commercial Department on all Variations issues
•Assist Project Control Manager and the Consortium for the interim of Extensions of Time (EoT) Claim
05/2002 – 12/2004 Planning Manager
Responsibilities:
•Review of Contracts on deliverable requirements
•Development and maintenance of Contract Programme for Rail Signalling and Centralised Traffic Control Centre (CTC) system
•Involvement in the Planning Delay Analysis exercise for Extension of Time (EoT) Claims
•Compilation and coordination of programme related inputs from all relevant parties
•Development and maintenance of internal programmes based on contract programme and revised access key dates, as well as editing of narrative
•Coordination and revision of programmes within the Consortium, and from Clients and Sub-Contractors.
•Monitoring, assessment and reporting of progress of Sub-Contractors
•Responsible for issuing monthly programme updates and progress reports to the Consortium
•Monitoring and assessment of all revised access dates schedules, including Infrastructure and Consortium partner’s programmes
•Monthly programme analysis of targets and alternative solutions
•Provision of statistical progress input to Commercial Department for monthly claim payment schedule
Provide assistance to Process Control Manager to improve relevant Project Procedures within the Quality Plan
•Provide training to the Document Control Manager and Process Control Manager on planning issues
SYZ Consortium (Siemens-YTL Consortium) 04/1999 – 04/2002 Programme Manager
Projects: Express Rail Link Project – Kuala Lumpur Sentral to Kuala Lumpur International Airport
Responsibilities:
•Study and identify all Employer Requirements and EPC (Engineering, Procurement and Construction) Contract of all deliverables for the contractual obligations of the project
•Planning and scheduling for Electrical & Mechanical Sub-systems for Traction Power Substation, Overhead Catenary, Telecommunication, Signalling, E&M Services, SCADA, Depot/Workshop, Rolling Stock (12 Train sets) and Project Management)
•Co-ordination System and Infrastructure Works schedules into Master Programme
•Co-ordination of subsystems during concept and detailed design phase
•Assist in development of Project Procedure Manual (PPM), an internal guideline for project management
•Production of monthly progress reports for Client and internal report for Steering Committee
•Development of graphical illustration of overall Master Implementation Programme using LINEA software version 3.0
•Assist Process Control Manager in Design Documentation Plan and Factory Acceptance Test Plans