Hello P6 experts,
is it possible to reset the Spending Plan and Benefit Plan entries in the Project Detail form, Spending Plan tab to Zero?
when I enter a new value, it is added to the existing one, e.g. 170 + 1 = 171, 170 + 0 = 170
I have already set to Zero all the values at the wbs level.
Thanks for your help,
Alexandre
is it possible to reset the Spending Plan and Benefit Plan entries in the Project Detail form, Spending Plan tab to Zero?
when I enter a new value, it is added to the existing one, e.g. 170 + 1 = 171, 170 + 0 = 170
I have already set to Zero all the values at the wbs level.
Thanks for your help,
Alexandre