Dear Rodel Sir.
I have 5000 manhours for piping .
however i do not know how many days and nos resources need to finished piping activities,
how to calculate duration and no of resource,
what i am try to do is.
i have piping activities which having 8 hr /day cal.
5000/8=625 days if one person work 8 hr per dya he need 625 dyas,
i assume i ahve 8 resource they will work 8 hr/ day =64 hr/day
mean 625/64=78 days,
nos resource are 8
nos of day OD is 78 days.
i have piping cost which is usd 204545.45
if i will divide 204545.45/5000=40.9 usd / hr.
is this is corect method to calculate resource and nos of day.
Please advise me your best how to handle this schedule it is Bid schedule
Kind regards
I have 5000 manhours for piping .
however i do not know how many days and nos resources need to finished piping activities,
how to calculate duration and no of resource,
what i am try to do is.
i have piping activities which having 8 hr /day cal.
5000/8=625 days if one person work 8 hr per dya he need 625 dyas,
i assume i ahve 8 resource they will work 8 hr/ day =64 hr/day
mean 625/64=78 days,
nos resource are 8
nos of day OD is 78 days.
i have piping cost which is usd 204545.45
if i will divide 204545.45/5000=40.9 usd / hr.
is this is corect method to calculate resource and nos of day.
Please advise me your best how to handle this schedule it is Bid schedule