Dear Rodel,
Please advise me about this subject:
Am I right if I compare performance % complete (physical % complete) vs schedule % complete???
Note:
- My schedule is cost loaded (calculate cost from units)
- I am measuring progress using physical % complete
- Schedule % complete come from my baseline schedule which is not progressed.
Thank you in afvance
Duy