Hi
I was going to update my schedule today.First I saved copy of my previous schedule in same node where my current project is.
Then Project..Maintain Baselines..Added saved project as baseline.
Then Project..Assign Baseline..as I put it as primary baseline.
Then I compare my current Finish with primary baseline finish(BL1 Finish) in primavera.Now I am facing two problem:
1)Variance shown in column"Variance BL1" in NOT right.It is taking data from somewhere else & is comparing with current finish date.Is there any default baseline settings too or why it is doing so??
2) Variance BL1 Finish=Current Finish-BL1 Finish It should be -vein case of slippage.But it is showing positive value why?.Example 12June 10 - 20June10=-ve Value.But it is showing postive over there.Why??
I was going to update my schedule today.First I saved copy of my previous schedule in same node where my current project is.
Then Project..Maintain Baselines..Added saved project as baseline.
Then Project..Assign Baseline..as I put it as primary baseline.
Then I compare my current Finish with primary baseline finish(BL1 Finish) in primavera.Now I am facing two problem:
1)Variance shown in column"Variance BL1" in NOT right.It is taking data from somewhere else & is comparing with current finish date.Is there any default baseline settings too or why it is doing so??
2) Variance BL1 Finish=Current Finish-BL1 Finish It should be -vein case of slippage.But it is showing positive value why?.Example 12June 10 - 20June10=-ve Value.But it is showing postive over there.Why??