Hi to all,
I assigned my cost throught Resource = Material to each & all activity.
But when i m going to update my activity (Activity % Complete)after having percentage of activity my cost is not showing from Budgeted Total cost coloumn.
pls reply any1
thanks...........;)
I assigned my cost throught Resource = Material to each & all activity.
But when i m going to update my activity (Activity % Complete)after having percentage of activity my cost is not showing from Budgeted Total cost coloumn.
pls reply any1
thanks...........;)