Hi,
I have a question.
We are using negative lags for example design to be finalised 60 days before Manufacture of First unit.
Manucture unit one FS(-60) Finalise design
Here the Predecessor of Finalise design is Manufacture unit one. What could I use as its successor so that Float values are good and real.
Thanks,
Vijay