Good Morning Planners,
as I understand, if there is an activity in main project has no corresponding activity in baseline project then that activity would not have any baseline dates. Please let me know I am wrong.
The question is if the situation is vice versa, i.e. baseline project holds an activity which is not present in main project then what happens? Also, does that makes any harm during future updatation of project like, add/delete activities and then update them in baseline project, duplication of activity id or any that sorts of trouble.
Another question is, if i delete an activity from main project, does it gets deleted from baseline project or not?
Many Thanks,
Kandarp
as I understand, if there is an activity in main project has no corresponding activity in baseline project then that activity would not have any baseline dates. Please let me know I am wrong.
The question is if the situation is vice versa, i.e. baseline project holds an activity which is not present in main project then what happens? Also, does that makes any harm during future updatation of project like, add/delete activities and then update them in baseline project, duplication of activity id or any that sorts of trouble.
Another question is, if i delete an activity from main project, does it gets deleted from baseline project or not?
Many Thanks,
Kandarp