I have imported a MS Project program in P6. But i noticed that the orginal duration of the project after importing is not changing , For example a duration is 15 , even if i change to 25 days , the early finish or nothing is affected..this applies to all activities......what is the solution for this type of problem....I have checked all this
a) Constraints
b) Project Window - Calculation tab - reset OD & REM. Units..& also reset remaining duration....
c) Checked all the user preferences tab etc.....
Still the problem presists, can anyone guide me...
regards,
Haresh Jayanth
I have imported a MS Project program in P6. But i noticed that the orginal duration of the project after importing is not changing , For example a duration is 15 , even if i change to 25 days , the early finish or nothing is affected..this applies to all activities......what is the solution for this type of problem....I have checked all this
a) Constraints
b) Project Window - Calculation tab - reset OD & REM. Units..& also reset remaining duration....
c) Checked all the user preferences tab etc.....
Still the problem presists, can anyone guide me...
regards,
Haresh Jayanth