Dear Experts,
I am currently facing an issue with one our programmes which was submitted by the contractor. This is an update, we have assigned the accepted baseline to it. As you might aware, the planned value can be viewed in a column which is a cumulative figure and also periodically in a table. These two values just before the data date should match but in this programme they are not matching. I tried to find out the reason for it but failed and I would appreciate if you advice the possible reason.
thanks & regards
Dinesh
I am currently facing an issue with one our programmes which was submitted by the contractor. This is an update, we have assigned the accepted baseline to it. As you might aware, the planned value can be viewed in a column which is a cumulative figure and also periodically in a table. These two values just before the data date should match but in this programme they are not matching. I tried to find out the reason for it but failed and I would appreciate if you advice the possible reason.
thanks & regards
Dinesh