I have been struggling with this MS Project for the last 1 week and have just found out this web-site.I would appreciate any help...
After entering all the project data,constraints and resource levelling.I am setting up a baseline. Right after that I update my project, however I cannot see teh cost and time variences in the baseline column. They are all shown 0%.
Any idea how I can fix this up?
Thanks