Hello Everybody,
I have an issue with importing Budgeted Labour units.
In my schedule I have Budgeted Labour units currently defiend in a UDF column. I am trying to export it in Excel and then re-import the values as Budgeted Labour Units.. (I have already assigned a resource to the activities).
However it doesnt work.
Any suggestions would be very helpful.
Thanks
Sue
I have an issue with importing Budgeted Labour units.
In my schedule I have Budgeted Labour units currently defiend in a UDF column. I am trying to export it in Excel and then re-import the values as Budgeted Labour Units.. (I have already assigned a resource to the activities).
However it doesnt work.
Any suggestions would be very helpful.
Thanks
Sue