Hai
1.I did Cost Loading For my Project.I am Able to Get the Correct Budget Cost in the Activity Table .But in My Activity Usage Profile Option/Resource Usage Profile I got Difference of 60SAR(Saudi Riyal)
2.When I Import the Same Project to Another PC I got Different Budget Cost & After that if i Run Global Change (Budget Cost = Budget Material Units * Price/Unit).I am able to get the Exact Value in Activity Table & In S Curve I got Same 60 SAR Diff
How can i Fix it.
Regards
Anbin Ponnith