Hi to all,
I was a Primavera SureTrak user now venturing into more capable software. Here I was limited to model resource usage using resource lag and resource duration. This I find very useful as it allows the software to reschedule resource usage according to recomputed activity dates on my updates.
Within SureTrak I do not have access to a resource usage/assigments table I can modify and wonder how it works under schedule updates on the other software.
Do edits in the resource assigments locks the resource usage to fixed dates overriding CPM logic on your updates? Could it happen under this circumstances that the software schedule resource usage with no regard to when the activity is to be rescheduled? Please be specific as to your software.
Best regards,
Rafael
I was a Primavera SureTrak user now venturing into more capable software. Here I was limited to model resource usage using resource lag and resource duration. This I find very useful as it allows the software to reschedule resource usage according to recomputed activity dates on my updates.
Within SureTrak I do not have access to a resource usage/assigments table I can modify and wonder how it works under schedule updates on the other software.
Do edits in the resource assigments locks the resource usage to fixed dates overriding CPM logic on your updates? Could it happen under this circumstances that the software schedule resource usage with no regard to when the activity is to be rescheduled? Please be specific as to your software.
Best regards,
Rafael