I have recently taken over another planners P6 programme. I have deleted all existing baselines and trying to take a project initial baseline (the programme has had actuals placed onto it already)
When I assign the new project baseline the dates do not match the Start/ Finish dates. The dates are taking the planned Start/ Planned Finish dates.
Why???
Does anyone know how I can baseline the current project dates, NOT the planned start/Finish dates.
Thanks