I have been struggling off late with exporting from P6.2.1 to MPP.
After the export, I get an error report message with text The argument value is not valid next to each activity.
On opening the MPP file I find that it has exported all the activities with relationship, however the duration of each activity is 1 day. I also didnt find the ACT ID in text 1 column - which I had specified :-(
Could anyone help me with detail procedure of exporting to MPP.
Thanks