Hi all;
Can anybody tell me why, I updated a programme, and I didnt created and assigned any base line. the assign baseline window has current project as the base line. but my start and finish for the current project activities are not matching with the baseline start and finish for the activities which are completed or in progress.
Can anybody tell me why, I updated a programme, and I didnt created and assigned any base line. the assign baseline window has current project as the base line. but my start and finish for the current project activities are not matching with the baseline start and finish for the activities which are completed or in progress.