Dear Sir,
I am very much new to primavera , so pls. help me.
I have a question on update of progress . consider following example.
Activity duration start date finish date resource
A1 10days 9/6/09 18/6/09 R1@8hr/day (1no. for 10days)
Now my questions are :-
If I want to update progress on 11/6/09 manually and came to know that A1 activity has correctly started on 9/6/09 but today it is just 20% complete ? What steps should I do to feed these details?
2) After feeding details , I already know that I am lagging behind in progress and as per plan 30% work is to be completed. What can I do to complete the work on right time in primavera?
3) Will I have to reschedule as per new changes and how can I compare new one with old one?
4) what happens of resource assign to this activity ?
Thanx in advance
I am very much new to primavera , so pls. help me.
I have a question on update of progress . consider following example.
Activity duration start date finish date resource
A1 10days 9/6/09 18/6/09 R1@8hr/day (1no. for 10days)
Now my questions are :-
If I want to update progress on 11/6/09 manually and came to know that A1 activity has correctly started on 9/6/09 but today it is just 20% complete ? What steps should I do to feed these details?
2) After feeding details , I already know that I am lagging behind in progress and as per plan 30% work is to be completed. What can I do to complete the work on right time in primavera?
3) Will I have to reschedule as per new changes and how can I compare new one with old one?
4) what happens of resource assign to this activity ?
Thanx in advance