Dear All,
My construction project says that calendar should be such that u have to do work 12h/day and 7days a week with no holiday for a duration of 1year. Now I have made calendar like this. As a next step I have made changes in admin preference and user preference as 12h / 84hweek/ 360hmonth/4320hyear . Is it correct ? or I have to take 28/29days and 31days also in count and then fill user and admin preference.?
Regards,
My construction project says that calendar should be such that u have to do work 12h/day and 7days a week with no holiday for a duration of 1year. Now I have made calendar like this. As a next step I have made changes in admin preference and user preference as 12h / 84hweek/ 360hmonth/4320hyear . Is it correct ? or I have to take 28/29days and 31days also in count and then fill user and admin preference.?