Hi Planners,
In P3 program, during review of contractors updated program, how do we know that there are no replacement of relationships between current and baseline program? Say 10,000 or more activities. Not using manual checking, is it possible in P3 to generate the report instantly for the differences of relationship?
Thanks in Advance,
Albert
In P3 program, during review of contractors updated program, how do we know that there are no replacement of relationships between current and baseline program? Say 10,000 or more activities. Not using manual checking, is it possible in P3 to generate the report instantly for the differences of relationship?