Good day Gentlemen,
I have a little problem with my schedule.
I currently have 4 sub projects (close to independent: as in there are no interelated activities) in a single project.
For each of them, I have a "mandatory Finish" Milestone which represents my contractual finish date for each sub project.
I also have a finish mileston which represents the actual finsh date of each sub project; which is also tied to the contractual finish milestone with a FF relationship.
I am now trying to show the Critical path of each sub project.
Issue encountered:
Since each sub project will finish earlier than the contractual date, they the sub projects activities will never show a o total float (unless if I constraints inside the project)
If I choose to show the Critial Path via the longest path, it will take the sub project that finishes the lastes and athe critical path run through that particula sub project only.
Would nayone here have a way of showing each sub projects critical path?
Thank you
Brian
I have a little problem with my schedule.
I currently have 4 sub projects (close to independent: as in there are no interelated activities) in a single project.
For each of them, I have a "mandatory Finish" Milestone which represents my contractual finish date for each sub project.
I also have a finish mileston which represents the actual finsh date of each sub project; which is also tied to the contractual finish milestone with a FF relationship.
I am now trying to show the Critical path of each sub project.
Issue encountered:
Since each sub project will finish earlier than the contractual date, they the sub projects activities will never show a o total float (unless if I constraints inside the project)
If I choose to show the Critial Path via the longest path, it will take the sub project that finishes the lastes and athe critical path run through that particula sub project only.
Would nayone here have a way of showing each sub projects critical path?
Thank you
Brian