when we update the program ( not the baseline), should we need to update the original duration !
my boss told me to do two scenarios :
1- use actual trend to calculate the new original duration.
2- keep the original duration untouched, thus how much "work" we need to respect the baseline.
any idea will be highly appreciated
best regards
mimoune