Hello Guys,
I have opened more than one projects. While in the activities window I have grouped them by project name. But when I try to sort them by the planned start date. They dont sort i.e. the project name bands dont move.
For example, I have created three projects A, B, C with planned start dates as follows:
A 01-Aug-09
B 04-Jan-09
C 01-Sep-09
When I open them at the same time and group by project. In the activities window the band appear in the sequence say C,A,B. How can I sort them so that they appear as B,A,C?
Thanks
Ijaz
I have opened more than one projects. While in the activities window I have grouped them by project name. But when I try to sort them by the planned start date. They dont sort i.e. the project name bands dont move.
For example, I have created three projects A, B, C with planned start dates as follows:
A 01-Aug-09
B 04-Jan-09
C 01-Sep-09
When I open them at the same time and group by project. In the activities window the band appear in the sequence say C,A,B. How can I sort them so that they appear as B,A,C?
Thanks
Ijaz