Here is the scenario:
Originally, activity A has a duration of 7 days and labor units of 100.
However, during the course of the construction, activity A takes 21 days to complete.
When updating and I put 14 days as the remaining duration, the activity does not earn any units...though in reality it does.
Is there a fix to this? Or should i just manually enter earned units (which does not seem right).