Dear all,
i want to monitor my project in the manner illustrated in the following example, i need help on which auto cost rules to change.
suppose activity is of excavation and scheduled days are 10 and budgeteg manhous(resource) is 100 hrs
At the end of 5 days the situation is like i gave RD(5 days) and percent completion of the task is 30% and the resource used is like 65 hrs
my question is that i want to keep the PCT, RD and actual quantity not linked with each other ....so which rules of auto cost i shall change