Hello
I have a question and I hope i get help.
I have an activity, which is FCU supply..the payment condition for its delivery is 25% down payment and 75% after one month from delivery, means i need to expand resource usage one month AFTER the activity has finished.
Any help? Im using P6.
What i did was divide the two payments into two resources, one with a curve that is 100% front loaded and budgeted quantity of 0.25 units, and the other 100% back loaded and with a budgeted quantity of 0.75 units but when I set original lag to 1 month for the 2nd resource, the activity finish date is delayed by 1 month too, which i dont want to happen.
Please share your advice
thank you
I have a question and I hope i get help.
I have an activity, which is FCU supply..the payment condition for its delivery is 25% down payment and 75% after one month from delivery, means i need to expand resource usage one month AFTER the activity has finished.
Any help? Im using P6.
What i did was divide the two payments into two resources, one with a curve that is 100% front loaded and budgeted quantity of 0.25 units, and the other 100% back loaded and with a budgeted quantity of 0.75 units but when I set original lag to 1 month for the 2nd resource, the activity finish date is delayed by 1 month too, which i dont want to happen.
Please share your advice
thank you