Hi
Im back on one of my favourite topics again - the Planned Percent Complete complete. Id thought Id got my head round how it works, but it appears not!
Currently, I show Percent Complete next to Planned Percent Complete. I enter progress into the Percent Complete column and expect the Planned Percent Complete column to show what I should have done on todays date. Instead the Planned Percent Complete is working to my Progress Period. How do I set the column to work to todays date instead?
Thanks, Laurie
Im back on one of my favourite topics again - the Planned Percent Complete complete. Id thought Id got my head round how it works, but it appears not!
Currently, I show Percent Complete next to Planned Percent Complete. I enter progress into the Percent Complete column and expect the Planned Percent Complete column to show what I should have done on todays date. Instead the Planned Percent Complete is working to my Progress Period. How do I set the column to work to todays date instead?
Thanks, Laurie