Hellow to All
My name is umer , i am currently working on the construction of Cement Plant . The civil work is only started as only foundations of some structures are complete. The design of super structure is delayed and we have only few elements drawings of the structures.
Keep in this background the client ask me to give area wise progress , i dont know that the area or buliding super sturcture ie how many beams and columns are there .
Now Question is how can i satsify my client as he insist on asking area wise percentage completion
your advised would be helpful for me
Thanks
Umer Mehmood
Civil Planning Engineer
My name is umer , i am currently working on the construction of Cement Plant . The civil work is only started as only foundations of some structures are complete. The design of super structure is delayed and we have only few elements drawings of the structures.
Keep in this background the client ask me to give area wise progress , i dont know that the area or buliding super sturcture ie how many beams and columns are there .
Now Question is how can i satsify my client as he insist on asking area wise percentage completion
your advised would be helpful for me
Thanks
Umer Mehmood
Civil Planning Engineer