Does anyone out there know of a real easy way of determining the activity status of a particular activity when viewing the activity via the resource assignments view?
The best that I can come up with is either a very convoluted filter or using a global change in the activities view to apply a code which I am then able to access in the resource assignments view, however this then becomes static data which requires the re-running of the global change prior to viewing this data.
Mark
The best that I can come up with is either a very convoluted filter or using a global change in the activities view to apply a code which I am then able to access in the resource assignments view, however this then becomes static data which requires the re-running of the global change prior to viewing this data.
Mark