Dear All,
Urgent need help...
Previously, I was using P6 for tender programme. The programme/schedule was done to satisfy only the tender requirements.
Now, am using P6 to prepare programme/schedule for construction phase. The 1st difficulty I encountered is structuring of the programme to suit cost and budget monitoring.
Please correct me:
We have nearly a hundred cost and/or budget codes. To track the performance of each cost code, I need to filter each code therefore there should be only one cost code per activity. The WBS must be patterned to the structure of the cost coding.
I can easily manipulate this exercise in P3 but in P6 I don’t have the confidence yet without taking the risk of double handling the task.
Your suggestion will be very much appreciated.
Cheers,
Nestor
Urgent need help...
Previously, I was using P6 for tender programme. The programme/schedule was done to satisfy only the tender requirements.
Now, am using P6 to prepare programme/schedule for construction phase. The 1st difficulty I encountered is structuring of the programme to suit cost and budget monitoring.
Please correct me:
We have nearly a hundred cost and/or budget codes. To track the performance of each cost code, I need to filter each code therefore there should be only one cost code per activity. The WBS must be patterned to the structure of the cost coding.
I can easily manipulate this exercise in P3 but in P6 I don’t have the confidence yet without taking the risk of double handling the task.
Your suggestion will be very much appreciated.
Cheers,
Nestor