Dear All,
In P6.1 whenever i Open a project, the activities are grouped as per the last opened project Grouping. If the last project was X and if i try to open Y project, the Y projects activities are grouped as per X project last activity grouping.
In Project Planner P3, whenever we open project the activities are organised as it was the last time i closed the project.
The only solution i could figure out is to save separate layout and open them, after opening the project.
Regards,
Bharath
In P6.1 whenever i Open a project, the activities are grouped as per the last opened project Grouping. If the last project was X and if i try to open Y project, the Y projects activities are grouped as per X project last activity grouping.
In Project Planner P3, whenever we open project the activities are organised as it was the last time i closed the project.
The only solution i could figure out is to save separate layout and open them, after opening the project.
Regards,
Bharath