Dear all
In P5 If I have an activity ID 44 will start Sep. 10, 2008 and will finish Sep. 12, 2008; this activity has a successor with relationship FS (finish to start) with
Activity ID 55 when I make a schedule command; Activity 55 will start on Sep. 12, 2008 I wonder why it is not start as expected on Sep. 13, 2008.
Can you help me to solve this problem?
Regards,
Abeer Mohamed Taher
In P5 If I have an activity ID 44 will start Sep. 10, 2008 and will finish Sep. 12, 2008; this activity has a successor with relationship FS (finish to start) with
Activity ID 55 when I make a schedule command; Activity 55 will start on Sep. 12, 2008 I wonder why it is not start as expected on Sep. 13, 2008.
Can you help me to solve this problem?
Regards,
Abeer Mohamed Taher