Hello everybody,
In Microsoft Project when i change the date of one activity the others activities change the start date automatically, but in P6 i can´t.
I go to Edit/User preferences and click Reorganize automatically, then press F5 and the activities don’t change.
So i choose the chart view, select all activities, right click/ reorganize all and the activities don’t change.
Tools/Reorganize now and nothing.
Any can hepl me please?
Regards,
Felipe