Friends,
I am using P3 for planning and scheduling. I have used the man-hours basis doing all the work. Now first time i want to use the cost resources like labour cost, material cost, equipment cost, subcontract cost and sundry cost for all activities (direct & indirect costs) and i want to create a cash flow from P3. Anybody help in the above matter or please give an idea for that?
Thanks & Regards,
VJ
I am using P3 for planning and scheduling. I have used the man-hours basis doing all the work. Now first time i want to use the cost resources like labour cost, material cost, equipment cost, subcontract cost and sundry cost for all activities (direct & indirect costs) and i want to create a cash flow from P3. Anybody help in the above matter or please give an idea for that?
Thanks & Regards,
VJ