I have many clients who are concerned that "Schedule % complete" is based on the baselines duration - whereas they would like it based on "work" or earned value.
I think I have a workaround.
Take a fresh copy of the unprogressed baseline.
Set all activities to "auto compute actuals"
Run Apply Actuals to the current data date.
Demote this version to being a baseline.
The "units % complete" from the baseline IS available - and with the "perfect" progress in the baseline plan, "units % complete" is the expected "performance % complete"
This should constitute "Planned % Complete"