Dear Friends,
Here is another interesting topic. How can we setup different "hours per time period" for different projects. The problem i faced was, in one project i want to specify the default hours as 10 and some projects are 8 hrs. I made 10hrs calender and 8 hrs calender.
Scenario:
I have a project which is having 10hrs work per day. So i have made a 10hrs calender for it. When i entered an activity of 2 days it should give me 2*budgeted units by default 10*2 =20 (using only one resource per activity and resource calender is also made for 10 hrs) here when u enter 20 hrs budgeted units the duration will be going to 3 days. And ofcource if you see the budgeted units / time in % it shows 125% . All makes crazy. Finally i found the default hours per time period in Time Units in User preference is set as 8 hrs per /day 40 hours per week etc etc. Now i went to admn preference and changed all to 10hrs perday 70hrs per week etc etc. OK. Now, I want to work on a different project which is having 8hrs per day only. So how can i set up different hours per time period for different projects........ I know you got mad now...but still i believe its an interesting topic.
Cheers
Suresh
Here is another interesting topic. How can we setup different "hours per time period" for different projects. The problem i faced was, in one project i want to specify the default hours as 10 and some projects are 8 hrs. I made 10hrs calender and 8 hrs calender.
Scenario:
I have a project which is having 10hrs work per day. So i have made a 10hrs calender for it. When i entered an activity of 2 days it should give me 2*budgeted units by default 10*2 =20 (using only one resource per activity and resource calender is also made for 10 hrs) here when u enter 20 hrs budgeted units the duration will be going to 3 days. And ofcource if you see the budgeted units / time in % it shows 125% . All makes crazy. Finally i found the default hours per time period in Time Units in User preference is set as 8 hrs per /day 40 hours per week etc etc. Now i went to admn preference and changed all to 10hrs perday 70hrs per week etc etc. OK. Now, I want to work on a different project which is having 8hrs per day only. So how can i set up different hours per time period for different projects........ I know you got mad now...but still i believe its an interesting topic.
Cheers
Suresh