Hello there! I am very desperate for help.I am new to planning and i am tasked to submit a substantiation report for our notice of delay. I included in my report the clause(s) in the contract related to the delay.I discussed the cause of delay and work delay. I also added and discussed the program i made from p3, the elements i added are the planned early start, early finish, actual start and finish, original duration and remaining duration, variance early start and total float. If you are to assess the program, what will you point out so that my claims for EOT will be denied? And how can i exactly show or calculate the number of delays in my substantion report? Please help. Please,please.
Regards,
den