Hi all, A few silly questions intended towards users of Suretrak. I am a bit new to Suretrak and have been trying to load resources mainly equipment on tasks not to define durations but so i could take out an equipment profile programme for the project. Not quite sure if i am doing it correctly.
1- I defined a crane as a resource with a limit of 1 for the project and set as non driving
2- Clicked on relevant task - details - resources and added the crane from the list. Changed budgeted qty=1 and to complete=1 as they had changed according to the duration already set. The unit/hr changes to 0.01
3- Now when i take out the resource profile it shows columns at 0.01 peak constant through out the period crane is being used. Should it not show 1 no. crane?
4- Is there any way of taking a gantt chart of resources out as can be done in Power Project?
5- Can quantities to complete (eq. cub-m of excavation) and equipment to do the work (eg. 1 no. excavator) be defined seperately in Suretrak?
Thanks
1- I defined a crane as a resource with a limit of 1 for the project and set as non driving
2- Clicked on relevant task - details - resources and added the crane from the list. Changed budgeted qty=1 and to complete=1 as they had changed according to the duration already set. The unit/hr changes to 0.01
3- Now when i take out the resource profile it shows columns at 0.01 peak constant through out the period crane is being used. Should it not show 1 no. crane?
4- Is there any way of taking a gantt chart of resources out as can be done in Power Project?
5- Can quantities to complete (eq. cub-m of excavation) and equipment to do the work (eg. 1 no. excavator) be defined seperately in Suretrak?
Thanks