hi,
if you remember to export data from p3 we should go to reoprts\tabular reports\resources and set the interval (week/month) and generate a wk1 or db file and edit in excel ...
now the problem I faced is how to do the same in P5!
I export from "resource assignments" and copy and paste to excel, but Id like to have a calculated early and late quantities (both) in excel at once.
any comments??
mp1j2000@yahoo.com [1]
if you remember to export data from p3 we should go to reoprts\tabular reports\resources and set the interval (week/month) and generate a wk1 or db file and edit in excel ...
now the problem I faced is how to do the same in P5!
I export from "resource assignments" and copy and paste to excel, but Id like to have a calculated early and late quantities (both) in excel at once.
any comments??
mp1j2000@yahoo.com [1]