Is there a way to plot one s-curve against percentage complete on one side and hours earned on the other in that it will automatically adjust the hourly scale to accomodate any added hours??
For example, in my line of work, we establish a baseline s-curve for the expected work against a calender. During the performance we are hit with added work and it adds to our total work scope. When we add the extra work in our schedule, obviously our budgeted man hours increase. I would like to be able to plot my earned manhours alongside my baseline expected manhours with the baseline staying at 100% and the earned climbing and falling as needed without having to go in and manually adjust the scale. Any help would be appreciated
For example, in my line of work, we establish a baseline s-curve for the expected work against a calender. During the performance we are hit with added work and it adds to our total work scope. When we add the extra work in our schedule, obviously our budgeted man hours increase. I would like to be able to plot my earned manhours alongside my baseline expected manhours with the baseline staying at 100% and the earned climbing and falling as needed without having to go in and manually adjust the scale. Any help would be appreciated