Hello all
Can all experienced planners advise me on this please.
Ive been working on huge project for the last 18 months as planner employed by the main contractor of the project. The project is now finishing, with overall duration of about 3 years. And the project is delayed with 6 months.
Now the company I work for has decided to put a claim for the delay.
At the same time I have been told by my bosses that I havent done my job very well and issued with a letter about this, and heard that they might terminate my contract.
Do you think that the company I am working for is trying to blame me for the delay of the project? Is it a general practice contractors to blame the planners? How does it work?
Can all experienced planners advise me on this please.
Ive been working on huge project for the last 18 months as planner employed by the main contractor of the project. The project is now finishing, with overall duration of about 3 years. And the project is delayed with 6 months.
Now the company I work for has decided to put a claim for the delay.
At the same time I have been told by my bosses that I havent done my job very well and issued with a letter about this, and heard that they might terminate my contract.
Do you think that the company I am working for is trying to blame me for the delay of the project? Is it a general practice contractors to blame the planners? How does it work?