Greetings Gurus,
Haing (in my opinion) beig spoilt and never having used MS Project Server 2003 in anger previously, I came across a funny little thing the other day which Im sure will be very easily explained.
One particular resource assignment on a 48 hour actiity had a required effort of 40 hours, however the percentage was displaying 116%, which to me seemed a bit odd.
Could someone please explain.
Thanks
Andy