Hey all,
On my project we have over a hundred different sub contractors and we are importing schedules from each one of them into P6
I am trying to standardise the resource codes that we use, this means that the resource needs to be very flexible in the unit rates as almost all the contractors have different rates.
I am trying to get the schedules quanity driven, thus using the cost units linked on the resource.
From what I can see I can only assign a limited number of Unit rates.
Any help would be appreciated.
Oli