I have 2 project files
(1) the monthly updated schedule
(2) the baseline auto updated for planned progress on same data date as that of the file 1.
Now i open the file 1 and assign file 2 as its target.
is it possible to filter all the activities that have started(percent complete GT 0%) in the target file from within file 1?