Guys
Looking for a bit of your collective expertise here.
I have a couple of questions as follows.
1. Detailed Summary Charts. Is it possible to have a summary bar that shows rolled up progress / manhours etc from lower levels ? I can get it to show a summary bar, but I can’t seem to have it show any summarised information.
2.More of a query regarding variations. How is this done with in the industry using P5 ? We are having problems coming up with a suitable strategy.
Take the variation hours and add them to the baselined hours - Loose any sense of reporting on what they were for.
Take the variations and add them in as seperate activities -fine in principle, we retain visability and reportability but as we time write against these activities it could be messy.
Any thoughts on how we might approach this ?
As always your advice is greatly appreciated !!
Cheers
Neil
Looking for a bit of your collective expertise here.
I have a couple of questions as follows.
1. Detailed Summary Charts. Is it possible to have a summary bar that shows rolled up progress / manhours etc from lower levels ? I can get it to show a summary bar, but I can’t seem to have it show any summarised information.
2.More of a query regarding variations. How is this done with in the industry using P5 ? We are having problems coming up with a suitable strategy.
Take the variation hours and add them to the baselined hours - Loose any sense of reporting on what they were for.
Take the variations and add them in as seperate activities -fine in principle, we retain visability and reportability but as we time write against these activities it could be messy.
Any thoughts on how we might approach this ?
As always your advice is greatly appreciated !!
Cheers
Neil